Microsoft has withdrawn from an agreement with Nscale to develop a planned AI data centre in Loughton, Essex, after delays in securing an electricity connection pushed the project’s expected power supply into the 2030s.
The decision leaves Nvidia-backed British AI infrastructure company Nscale without its expected anchor customer for the facility, which raises further questions about the project’s timeline and the UK’s ability to support the growing demand for AI computing infrastructure.
The development also highlights a growing challenge for data centre operators as they race to build the infrastructure needed to support AI services. While access to advanced processors and computing equipment remains important, securing enough electricity to operate these facilities has equally become a major obstacle in several markets.
Grid Delays Force Microsoft to Abandon Agreement
The proposed Loughton data centre was part of a partnership between Microsoft and Nscale announced in September 2025. The facility was expected to provide 50 megawatts of AI computing capacity, powered by 23,040 Nvidia GB300 graphics processing units (GPUs), to support Microsoft’s Azure cloud services in the UK.
The project was initially expected to begin operations in early 2027. However, electricity supply problems have delayed its expected connection to the national grid.
UK Power Networks, which operates the electricity distribution network across London and south-east England, reportedly informed Nscale that the site would not receive the required power until the 2030s.
This made it difficult for the project to meet its original operating timeline, prompting Microsoft to terminate its agreement for the Loughton facility.
Microsoft clarified that the decision concerned only the Essex development and did not affect its wider relationship with Nscale, saying it remained committed to working with the infrastructure provider to develop digital infrastructure and support AI growth globally.
Nscale also maintained that its relationship with Microsoft remained strong and long-term, adding that the electricity supply problem would not affect its other contracts.
“Our relationship with Microsoft remains strong and long-term, and this unfortunate London-wide grid issue has no impact on our other contracts,” a spokesperson for Nscale told Reuters.
“We remain committed to both the Loughton project and the UK, and we are exploring alternative power sources for the site, as well as other expansion sites in the UK,” the spokesperson added.
Nscale Discloses $3.22 Billion Contract Termination
The financial impact of Microsoft’s withdrawal became clearer in a November 12 filing with the U.S. Securities and Exchange Commission (SEC), in which Nscale disclosed that the terminated agreement was worth approximately $3.22 billion.
However, the termination does not affect Nscale’s other agreements with Microsoft. According to the filing, the two companies had entered into separate statements of work worth up to approximately $43.8 billion in payments through December 2033.
The development comes as Nscale prepares for a potential public listing in the United States. Losing an agreement worth billions of dollars adds pressure to the company’s efforts to demonstrate that it can deliver the infrastructure needed to fulfil its large customer commitments.
UK’s Electricity Constraints Raise Concerns for AI Infrastructure
The setback also draws attention to the electricity supply challenges facing Britain’s growing data centre industry.
AI data centres require substantial amounts of electricity to operate the servers and GPUs used to train and run AI models. And as demand for these services increases, technology companies are investing heavily in facilities that can provide the computing capacity required by businesses and AI developers.
However, connecting new facilities to the electricity grid can take years, particularly in areas where existing infrastructure cannot accommodate additional demand.
According to Reuters, grid connection bottlenecks have delayed data centre projects in the UK by as much as 13 years. These delays could affect the ability of infrastructure developers to meet customer delivery schedules and bring new computing capacity online when expected.
For the UK government, this situation serves as a challenge to its plans to establish the country as a major destination for AI investment, especially as the Loughton project was among the developments highlighted as part of those ambitions when it was announced in 2025.
While Nscale still intends to pursue the Essex development, its ability to secure an alternative power supply remains a determinant of the facility becoming operational.